Building Face-Lift |
|
|
|
To cap-off our 75th Anniversary celebration in 2009, we are giving our building a Face-Lift. There are new, decorative stone supports with wood pillars around the building, as well as new decorative concrete to walk on. Here is a picture-by-picture look at our progress from beginning on September 29 to finish on November 28.
East View, from the Practice Green...
Work began on September 29th. The old wood pillars and supports were taken out, and temporary roof supports were installed. Then, on October 3rd, the old concrete slabs were removed.
 |
 |
|
September 29th
|
October 3rd |
Here's a close-up of the walkway transformation along the east side of the building. Check out the Zigfield Troy logo imprinted in the textured concrete.
 |
 |
|
October 3rd
|
November 8th |
By October 9th, new concrete slabs were poured with footings for the new stone supports, which began going up by October 13th.
 |
 |
|
October 9th
|
October 13th |
By November 8th, the wood pillars were installed on top of the stone supports. New gutters and downspouts would soon be linked to the underground drainage system.
 |
 |
|
November 8th
|
November 28th |
North View, from the Parking Lot...
 |
 |
|
September 29th
|
October 13th |
 |
 |
|
November 8th
|
November 28th
|
West View, from the flower garden...
 |
 |
|
September 29th
|
October 9th
|
 |
 |
|
October 13th
|
November 8th
|
 |
|
November 28th
|
Work on the stone pillar supports and stone bench continued just outside the Pro Shop entrance through October. The caps on each stone pillar support were installed in early November. Check out the different colors and textures in the concrete slab.
 |
 |
|
October 14th
|
November 18th
|
Front View, from the tree next to the Practice Green...
 |
 |
|
October 13th
|
November 8th |
Now that the project is complete, we want to remind you that the range is open year-round so you can keep your game sharp for next spring. New partitions along the sides of the building block the wind so you can practice in comfort. And we have six mats under heaters for additional comfort (heat costs just a dollar). Our Winter hours are 9AM until 5PM every day of the week.
 |
|
West entrance, with clear, air-tight sections to block the winter winds.
|
 |
|
Six hitting stations under the heaters. You can practice outdoors without getting battered by the winter winds.
|
 |
|
Front view showing the new side protection on both sides of the building.
|
|
|